Let's start with an example of a grocery mart. It's a greenfield implementation.
A grocery mart with 3 stores takes stocks from 10 vendors and sells them to retail customers.
This is a simple example of how SAP implementation is done.
The business owner talks to a SAP Consulting company.
Step 1: Project Preparation
SAP team talks to each department of the company to identify their pain points. This stage is called Project preparation.
Activities:
Assemble the Project Team:
Assign key roles:
SAP Project Manager.
Functional Consultants (FICO, MM, SD, HCM).
Technical Consultants (ABAP, Basis, BI).
Key Business Stakeholders.
Define Goals and Objectives:
Document business goals (e.g., automate inventory, improve financial tracking, unify sales data).
Set clear success criteria for the implementation.
Set Up the SAP Environment:
Install SAP systems (Development, Quality, Production).
Ensure infrastructure readiness: servers, databases, and access.
Develop a Project Plan:
Create a detailed timeline with milestones for each phase.
SAP Landscape Setup: Development (DEV), Quality Assurance (QAS), and Production (PRD) environments.
Step 2: Blueprinting
SAP team will prepare a Business Blueprint.
Activities:
Conduct Business Workshops:
Engage with Mart team to understand their current processes.
Identify gaps and challenges.
Document To-Be Processes:
Map business processes to SAP modules (e.g., inventory to SAP MM, sales to SAP SD).
Define workflows, approvals, and customizations needed.
Identify Master Data:
Create a list of master data requirements:
Finance: Chart of accounts, vendor, and customer data.
Inventory: Material master, purchase info records.
HR: Employee master data.
Finalize the Blueprint:
Document process flows, integration points, and reporting needs.
SAP Blueprint Document: Finalized business process document.
Step 3: Realization (Configuration and Customization)
Activities:
Configure Core SAP Modules:
SAP FICO:
Define chart of accounts, fiscal year variant, and payment terms.
Configure accounts payable and accounts receivable workflows.
SAP MM:
Set up material master, procurement types, and stock management.
Configure purchasing groups, vendors, and goods receipt processes.
SAP SD:
Set up sales orders, delivery processes, and billing types.
Define pricing conditions, tax rules, and customer master data.
SAP HCM:
Configure payroll, attendance tracking, and leave management.
Enable employee self-service portals.
SAP BI:
Create dashboards for sales, inventory, and financial reporting.
Develop Custom Enhancements:
Work with ABAP developers to create custom reports, workflows, and forms (e.g., custom invoice templates).
Perform Integration:
Integrate SAP modules (e.g., MM and FICO for procurement costs; SD and FICO for revenue tracking).
Step 4: Data Migration
Activities:
Prepare Data Templates:
Use SAP tools like LSMW (Legacy System Migration Workbench) or Data Services to prepare templates.
Cleanse and Validate Data:
Ensure data from existing systems is accurate and free of duplicates.
Upload Master Data:
Migrate master data into SAP:
Vendors, customers, and materials for MM and SD.
Employee data for HCM.
Chart of accounts for FICO.
Test Data Accuracy:
Verify data consistency in SAP systems after migration.
Step 5: Testing
Activities:
Unit Testing:
Test individual modules to ensure configurations work as expected.
E.g., Test a purchase order workflow in SAP MM.
Integration Testing:
Test end-to-end processes across modules:
E.g., Create a sales order (SD), update stock (MM), and track revenue (FICO).
User Acceptance Testing (UAT):
Allow Mart employees to test processes using real-world scenarios.
Gather feedback for adjustments.
Fix Issues:
Address any errors or gaps discovered during testing.
Step 6: Training
Activities:
Prepare Training Materials:
Create user manuals and step-by-step guides for each module.
Conduct Training Sessions:
Train employees on their specific roles in SAP:
Finance team for FICO.
Store managers for MM and SD.
HR team for HCM.
Enable Role-Based Access:
Assign SAP user roles and permissions based on job responsibilities.
Step 7: Go-Live
Activities:
Final Data Load:
Migrate live transactional data (e.g., open POs, pending sales orders).
Go-Live:
Switch to the SAP system for daily operations.
Monitor Performance:
Ensure all modules are functioning correctly during the initial phase.
Step 8: Post-Go-Live Support
Activities:
Provide Ongoing Support:
Address issues raised by employees during the transition period.
Refine configurations if needed.
Monitor System Performance:
Ensure system uptime and resolve technical glitches.
Review Project Success:
Compare actual performance with project goals.
Project Timeline
Phase | Duration | Activities |
Preparation | 1 Month | Team setup, project planning, and SAP landscape installation. |
Blueprinting | 1 Month | Business process mapping and documentation. |
Realization | 3 Months | Configure modules, develop customizations, and perform integrations. |
Data Migration | 1 Month | Migrate master and transactional data to SAP. |
Testing | 1.5 Months | Perform unit, integration, and UAT testing. |
Training | 1 Month | Train employees and assign system roles. |
Go-Live and Support | 1 Month | Launch the SAP system and provide post-go-live support. |